Entering Construction stage

We were penalised $2000 for delays to the start date. Apparently we were supposed to start in March, but because it’s May, they have penalised us $1000 per month past the start date. I argued that the delay was caused by KC not replying promptly… according to my calculations, we were waiting over 4 months …
Continue reading Entering Construction stage

Hygienist Clearance Certificate for Asbestos

Finally got everything out of the way. Our KC consultant quit and we got a new consultant who replies within a few hours of our emails! I think if we had this consultant right from the beginning, we would have started construction months ago! We’re finally entering the final stages now. We have signed off …
Continue reading Hygienist Clearance Certificate for Asbestos