Slab’s all done and it looks good (was actually completed on July 8 but didn’t take photos till today). I have been told though that materials for the frame won’t arrive till December! That’s 5 months away!
So 5 months of extra rent, and since we sold our house to build, that’s 5 months of no negative gearing and extra tax on interest. What’s more, PD won’t count this as a delay to our build because it’s out of their control, so they won’t be paying us $250 a week because of this delay.
I’m just hoping that they don’t take shortcuts once they restart building, just because they’re behind.