The blue wrapping looks like it’s completed upstairs now so the entire interior is not protected from the weather. All windows are in, except the main dining room window. There is a reason for that though. I was told that the steel beams were too close together (they’re 2.4m apart from top to bottom). The …
Continue reading More work done upstairs
Month:January 2023
Work starting on the upstairs
Looks like more work is now being done upstairs… window’s are all in and some shower bases have been installed. More of the blue lining downstairs too. Also noticed that more plumbing was done with the sewage pipes installed.
Back from holiday
We went overseas for the Christmas break and came back mid January. During that time, I thought there wouldn’t be much done because it was Christmas. But I was wrong… looks like a lot of work was completed while we were away. The downstairs windows are all in, the roof is finished (scaffolding all removed), …
Continue reading Back from holiday