Every day, more bricks are laid… seems like only brickwork being done the last few weeks.
Bricks at half way mark
More bricks laid…
More bricks laid
Almost half way up the house now…
Large window frames are in
Window frames are now installed.
More bricks laid today
Mortar still wet when I took the pictures. Side of the house where the hot water system is.
Starting to lay the bricks
Equipment arrived to start laying bricks. Also got the picture window frames.
Bricks delivered
Bricks delivered on Feb 6
Sparkies delayed
Just got a call today (3/2/23) from our SS to advise that the sparkies just went in today after a 2 week delay… no word yet for the brickies. Received an email advising of extension of time. I guess this is to advise us that they will not compensate us because of delays that is …
Continue reading Sparkies delayed
More work done upstairs
The blue wrapping looks like it’s completed upstairs now so the entire interior is not protected from the weather. All windows are in, except the main dining room window. There is a reason for that though. I was told that the steel beams were too close together (they’re 2.4m apart from top to bottom). The …
Continue reading More work done upstairs
Work starting on the upstairs
Looks like more work is now being done upstairs… window’s are all in and some shower bases have been installed. More of the blue lining downstairs too. Also noticed that more plumbing was done with the sewage pipes installed.